Rooppur 1 reaches criticality, with grid connection still to come
Bangladesh’s first nuclear reactor has begun a sustained chain reaction. It must pass further tests before power can be supplied to the national grid.

At Rooppur in Bangladesh, the first reactor at the country’s nuclear power plant has achieved criticality, marking the start of a sustained nuclear chain reaction. The milestone came three days after the national nuclear regulator gave the go-ahead, but it does not mean the unit is supplying electricity.
The reactor must now complete tests and safety checks before it is tested at its minimum controllable capacity. If those tests are successful, power supply to the national grid is expected to advance in stages, according to a statement on the project’s official Facebook account.
The power start-up is scheduled for 20 November, according to Strana Rosatom, the Russian state nuclear corporation’s in-house publication. Further checks are planned before start-up and as the unit’s output is raised. The plant is intended to diversify Bangladesh’s electricity generation and strengthen energy security, the project statement said.
What criticality means
Criticality means the reactor has reached a self-sustaining chain reaction: fission in the uranium fuel releases enough neutrons to keep the sequence going. It is a key step in starting up a reactor, but further testing is needed before the unit can move towards supplying power. Rosatom chief executive Alexey Likhachev said successful completion of this phase would leave the unit ready for the power start-up phase and later connection to Bangladesh’s grid.
What happens before grid supply
Bangladesh’s nuclear regulator issued the operating licence on 16 April this year. Loading 163 nuclear fuel assemblies into the reactor was completed in May. The first batch of fuel had arrived at the site in October 2023, when it gained the status of a nuclear facility. The latest milestone followed talks in Moscow between Likhachev and Science and Technology Minister Fakir Mahbub Anam.
Rooppur is about 160 kilometres from Dhaka. Rosatom signed an agreement in 2011 to build two reactors for the Bangladesh Atomic Energy Commission; construction of the first unit began in November 2017 and the second in July 2018. Rosatom also said on 12 October that automated process control systems had been installed at both units. The date when the first unit will begin supplying electricity to the grid has not been announced.
This report draws on information from World Nuclear News and energynews.pro.